You're reading: Olympiysky National Sports Complex 70% finished

Work on the reconstruction of the Olympiysky National Sports Complex in Kyiv is proceeding in line with the approved schedule and is currently 70% finished, the complex said in a press release.

According to the report, in particular, work on the fan servicing area is 76% finished, the VIP zone 64%, the underground parking lot 41%, the cold zone facilities (stands) 69%, load-bearing walls 98%, and a bypass road with an overpass is 88% finished.

According to the press service, builders have finished over 45% of the work on the stadium’s engineering systems, as well as 35% of the work on the development of the territory, including granite paving, the development of roads and footpaths, drainage systems, and exterior lighting.

Deputy Prime Minister and Infrastructure Minister Borys Kolesnikov said earlier that the Olympiysky National Sports Complex was to be opened on Independence Day on August 24.