You're reading: Defects delay Russian aircraft carrier delivery to India
Popular
on social media

“Fixing the problem entails changing the engines or
repairing them. It will take around nine months, maybe more
maybe less, but definitely more than six months,” one source
close to arms exporter Rosoboronexport told Reuters.

“That’s why the promised delivery of the ship by the end of
this year wont happen.”

Kommersant newspaper reported that defects on the ship,
Vikramaditya, were discovered during a sea test when the vessel
accelerated to maximum speed and its emergency warning system
sounded.

Exclusive article

Sign up or subscribe to view more articles.
Try Kyiv Post for just 99¢ for the first month!
See All Plans
$5.95
Monthly plan
Get unlimited article access, anytime, anywhere.

Subscribe
$60
Yearly plan
Access all the exclusive content on KyivPost.com and the complete online archive.
Subscribe
Advertisement

Add comment

Sorry, you must be logged in to post a comment.
More in this section
Attention

Add a picture
Choose file
Add a quote
Attention

Are you sure you want to delete your comment?

Attention

Are you sure you want to delete all user's comments?

Attention

Are you sure you want to unapprove user's comment?

Attention

Are you sure you want to move to spam user's comment?

Attention

Are you sure you want to move to trash user's comment?

Spelling error report

The following text will be sent to our editors: