Share Tweet Pocket Add to Bookmarks
You're reading: Chornobyl nuclear power plant site to be cleared by 2065
Popular
on social media

According to the law, the program is aimed at implementing government policy to protect staff, the surrounding population, and the environment from radiation from the Chornobyl NPP.

The program will be implemented in several stages. The first stage envisages the removal of nuclear fuel to storage facilities. This is to be completed no earlier than 2013. The second stage envisages the final closure and deactivation of reactors by 2022. The third stage (by 2045) involves maintaining the reactors until radiation drops to acceptable levels. The final stage (by 2065) involves dismantling the reactors and clearing the site to ensure that restrictions and regulatory controls are lifted to the maximum extent possible.

Subscribe now

Sign in or subscribe to view this article
See All Plans
$5.95
Monthly plan
Get unlimited article access, anytime, anywhere.

Subscribe
$60
Yearly plan
Access all the exclusive content on KyivPost.com and the complete online archive.
Subscribe
Advertisement

Add comment

Sorry, you must be logged in to post a comment.
More in this section
Attention

Add a picture
Choose file
Add a quote
Attention

Are you sure you want to delete your comment?

Attention

Are you sure you want to delete all user's comments?

Attention

Are you sure you want to unapprove user's comment?

Attention

Are you sure you want to move to spam user's comment?

Attention

Are you sure you want to move to trash user's comment?

Spelling error report

The following text will be sent to our editors: