The Cabinet of Ministers of Ukraine has approved a revised project of the construction of Terminal D at Boryspil International Airport, which foresees the increase in the cost of construction by 16%, to Hr 856 million and JPY 27.825 billion ($361.91 million), according to the press service of the Infrastructure Ministry.
The government made the decision at a meeting on Monday.
According to the new project, the terminal area will grow by 20%, to 107,000 square meters, a VIP zone will be made in the terminal.
In addition, the updated document foresees the possibility of servicing both international and domestic flights.
The terminal will have a parking lot for 233 cars.
At the same time, the ministry voiced the same term the construction is to be completed – December 2011.
It is planned to perform the first flight from the new terminal on March 25, 2012.